Quick answer: Budget at Completion (BAC) is the total approved budget for the work in a project or defined project scope. In earned value management, BAC provides the baseline budget figure used in several cost-performance calculations.
What Does BAC Mean?
BAC = Budget at Completion. It represents the planned budget for completing the scoped work, based on the approved performance measurement baseline. It is not the same as the amount already spent.
How Is Budget at Completion Calculated?
When building a project budget from work packages or control accounts, BAC can be understood as the sum of the approved budgeted amounts included in the project baseline:
BAC = Sum of approved baseline budgets for the defined work
If a project has baseline budgets of $20,000, $35,000 and $45,000 for three work packages, BAC is:
$20,000 + $35,000 + $45,000 = $100,000
BAC vs Actual Cost
Actual Cost (AC) is what has actually been spent for work performed. BAC is the approved budget for the complete scoped work. Comparing the two directly before completion does not by itself show whether the project is performing efficiently; earned value metrics provide more context.
BAC vs Estimate at Completion (EAC)
BAC is the baseline budget. Estimate at Completion (EAC) is a forecast of what the project is currently expected to cost at completion. If performance changes, EAC can differ from BAC.
Variance at Completion Formula
A common relationship is:
VAC = BAC − EAC
If BAC is $100,000 and EAC is $112,000:
VAC = $100,000 − $112,000 = −$12,000
A negative VAC indicates that the current completion estimate is above the baseline budget.
BAC Example With Earned Value Data
| Metric | Example value |
|---|---|
| BAC | $200,000 |
| Earned Value (EV) | $90,000 |
| Actual Cost (AC) | $100,000 |
The cost performance index in this example is EV ÷ AC = 0.90. If a forecasting method assumes the same cost efficiency continues, one possible EAC formula is BAC ÷ CPI, giving approximately $222,222. The appropriate EAC method depends on the forecasting assumptions being used.
When Can BAC Change?
BAC should not be casually changed to hide cost performance. It can change when the approved baseline is formally revised, for example after authorized scope or baseline changes under the project’s change-control process.
Common BAC Mistakes
- Treating BAC as money already spent.
- Confusing BAC with the latest forecast, EAC.
- Changing the baseline simply because actual costs are unfavorable.
- Mixing approved baseline values with unapproved scope.
- Using an EAC formula without understanding its performance assumptions.
Frequently Asked Questions
Is BAC the total project budget?
In earned value usage, BAC is the total approved budget for the work represented by the performance measurement baseline. Organizations may use broader financial-budget terminology differently, so check the project-control framework being used.
What happens when EAC is higher than BAC?
The current forecast exceeds the baseline budget, producing a negative VAC under the formula BAC − EAC.
Is BAC a forecast?
No. BAC is a baseline budget value; EAC is a completion forecast.
Last reviewed: October 2026. Apply the definitions and controls required by your organization’s project-management framework.